November 12, 2021
Building Permit Approval from the city of Coldwater.
December, 3 2021
Ground Breaking Ceremony
January, 2022
Pouring Concrete for Foundation Walls
April, 2022
Started to erect the steel for the whole building
June, 2022
Erecting the steel for school and gym’s roofing
September, 2022
Underground blumping was completed and started to pour the concrete for slab floor
October, 2022
Started the Exterior Framing
November, 2022
Started installing the dense glass for the whole building
December, 2022
Started the HVAC work
March, 2023
Started installing the windows for the School Section, Alhamdulillah.
April, 2023
Flat Roof is Completed, Alhamdulillah.
May, 2023
Started Interior Framing along with working on HVAC,
Alhamdulillah.
June, 2023
Started Electric Work
July, 2023
Installed more windows, and 75% completion of Skylights.
As of December, 2023
As of June, 2024
As of December, 2024
As of June, 2025