Projects

November 12, 2021

Building Permit Approval from the city of Coldwater.

December, 3 2021

Ground Breaking Ceremony

January, 2022

Pouring Concrete for Foundation Walls

April, 2022

Started to erect the steel for the whole building

June, 2022

Erecting the steel for school and gym’s roofing

September, 2022

Underground blumping was completed and started to pour the concrete for slab floor

October, 2022

Started the Exterior Framing

November, 2022

Started installing the dense glass for the whole building

December, 2022

Started the HVAC work

March, 2023

Started installing the windows for the School Section, Alhamdulillah.

April, 2023

Flat Roof is Completed, Alhamdulillah.

May, 2023

Started Interior Framing along with working on HVAC, 

Alhamdulillah.

June, 2023

Started Electric Work

July, 2023

Installed more windows, and 75% completion of Skylights.

As of December, 2023