Underground blumping was completed and started to pour the concrete for slab floor
Started installing the dense glass for the whole building
Started the HVAC work
Started installing the windows for the School Section, Alhamdulillah.
Flat Roof is Completed, Alhamdulillah.
Started Interior Framing along with working on HVAC,
Alhamdulillah.
Started Electric Work
Installed more windows, and 75% completion of Skylights.